Free scaffolding RAMS template

Written to SG4:22 Revision A. Covers the safe-zone sequence and the 7-day inspection duty a principal contractor asks about.

From section 3 of the file10 numbered sections
Scaffolding risk assessment and method statementEvery row starts with a score
Site access, unloading and other trades12 6Falls while erecting, altering or dismantling25 10Falls from an incomplete or part-dismantled scaffold20 5Falls from the completed scaffold in service20 5Falling components, materials and tools20 10

Risk with no controls, then with them. Check both against this scaffold.

20 hazard rows · 13 method steps · 23 source links

Get the scaffolder Word template

The trade-wide scaffolder document, not a per-job one. Your email is saved before the download appears.

So we can tell you if we find a mistake in a file you already hold. No marketing.

We store your email as set out in the privacy notice and delete it after 90 days.

What does the scaffolding file cover?

Part of the fileAlready writtenYou add
Risk assessment20 scaffolding hazard rows with controls and an opening 5 x 5 score eachScores you disagree with, plus hazards this scaffold adds
Method statement13 steps from design check to strike-out, SG4:22 safe zone includedThe lift-by-lift sequence, tie positions and hold points
Rescue planPrompts for suspension in a harness and for a collapseNamed rescuers, the equipment and how long it takes
Inspection recordA table for first-use, 7-day and post-event entriesThe inspections themselves
Reference points23 links, including SG4:22, WAHR reg 12, LOLER reg 9 and GS6Your document reference, or delete section 10 if the principal contractor wants only the assessment and method

How much can a scaffold hold?

Assume general purpose unless told otherwise.

DutyLoad per square metreRoughly
Inspection, very light duty0.75 kN/m²75 kg/m²
Light duty1.5 kN/m²150 kg/m²
General purpose2.0 kN/m²200 kg/m²
Heavy duty, masonry and cladding3.0 kN/m²300 kg/m²

0.75 and 3.0 are HSE’s examples; 1.5 and 2.0 are the TG20 classes between. Only two lifts of a TG20:21 scaffold may be worked at once.

What do you add before handover?

Attach the TG20:21 compliance sheet or the designer's drawing, write the lift-by-lift sequence and tie positions, and replace every edit prompt. A competent scaffolder signs it off and briefs the gang.

Where does the template stop?

Not a scaffold design. It cannot calculate a tie pattern or make a principal contractor accept the document.